137ft Luxury Motoryacht
Project Summary
Scope of Works:
- All Tanks cleaned for Survey Inspection 
- Engine Room Bilge Cleaning & Refinishing 
- Genset Cradles & Tank Tops Refinish 
- Davit Crane Sandblast and Refinish with Alex Seal Coating 
- Various Voids Cleaning and Refinishing 
- Parts and Machinery Components Refinishing 
- Painting of Lockers 
Project Timeframe:
- April - May 2018 [9 Days Total] 
- August 2018 [2 Days Total] 
TANK CLEANING FOR SURVEY INSPECTION BEFORE
TANK CLEANING FOR SURVEY INSPECTION BEFORE
TANK CLEANING FOR SURVEY INSPECTION BEFORE
TANK CLEANING FOR SURVEY INSPECTION AFTER
TANK CLEANING FOR SURVEY INSPECTION AFTER
TANK CLEANING FOR SURVEY INSPECTION AFTER
TANK CLEANING FOR SURVEY INSPECTION BEFORE
TANK CLEANING FOR SURVEY INSPECTION BEFORE
TANK CLEANING FOR SURVEY INSPECTION BEFORE
TANK CLEANING FOR SURVEY INSPECTION AFTER
TANK CLEANING FOR SURVEY INSPECTION AFTER
TANK CLEANING FOR SURVEY INSPECTION AFTER
TANK TOP REFINISH BEFORE
TANK TOP REFINISH BEFORE
ENGINE ROOM BILGE CLEAN & REFINISH BEFORE
ENGINE ROOM BILGE CLEAN & REFINISH BEFORE
ENGINE ROOM BILGE CLEAN & REFINISH BEFORE
TANK TOP REFINISH AFTER
TANK TOP REFINISH AFTER
ENGINE ROOM BILGE CLEAN & REFINISH AFTER
ENGINE ROOM BILGE CLEAN & REFINISH AFTER
ENGINE ROOM BILGE CLEAN & REFINISH AFTER
 
                         
             
             
             
             
             
             
             
             
             
             
             
             
             
             
             
             
             
             
             
             
             
             
             
  
  
    
    
     
  
  
    
    
     
  
  
    
    
     
  
  
    
    
     
  
  
    
    
    